Schedule network analysis

Schedule network analysis

Below are the description of all the uses of the working document “Schedule network analysis”:

“Schedule Network Analysis” is a tool/technique for the process “Develop Schedule”.
Schedule network analysis is a technique that generates the project schedule model. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource optimization techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities.
Some network paths may have points of path convergence or path divergence that can be identified and used in schedule compression analysis or other analyses.

This definition was found in the PMBOK V5