Forecasting

Forecasting

Below are the description of all the uses of the working document “Forecasting”:

“Forecasting” is a tool/technique for the process “Control costs”.
As the project progresses, the project team may develop a forecast for the estimate at completion (EAC) that may differ from the budget at completion (BAC) based on the project performance. If it becomes obvious that the BAC is no longer viable, the project manager should consider the forecasted EAC. Forecasting the EAC involves making projections of conditions and events in the project?s future based on current performance information and other knowledge available at the time of the forecast. Forecasts are generated, updated, and reissued based on work performance data that is provided as the project is executed. The work performance information covers the project?s past performance and any information that could impact the project in the future.
EACs are typically based on the actual costs incurred for work completed, plus an estimate to complete (ETC) the remaining work. It is incumbent on the project team to predict what it may encounter to perform the ETC, based on its experience to date. The EVM method works well in conjunction with manual forecasts of the required EAC costs. The most common EAC forecasting approach is a manual, bottom-up summation by the project manager and project team.
The project manager?s bottom-up EAC method builds upon the actual costs and experience incurred for the work completed, and requires a new estimate to complete the remaining project work. Equation: EAC = AC + Bottom-up ETC.
The project manager?s manual EAC is quickly compared with a range of calculated EACs representing various risk scenarios. When calculating EAC values, the cumulative CPI and SPI values are typically used. While EVM data
quickly provide many statistical EACs, only three of the more common methods are described as follows: – EAC forecast for ETC work performed at the budgeted rate. This EAC method accepts the actual project performance to date (whether favorable or unfavorable) as represented by the actual costs, and predicts that all future ETC work will be accomplished at the budgeted rate. When actual performance is unfavorable, the assumption that future performance will improve should be accepted only when
supported by project risk analysis. Equation: EAC = AC + (BAC ? EV) – EAC forecast for ETC work performed at the present CPI. This method assumes what the project has experienced to date can be expected to continue in the future. The ETC work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. Equation:
EAC = BAC / CPI – EAC forecast for ETC work considering both SPI and CPI factors. In this forecast, the ETC work will be performed at an efficiency rate that considers both the cost and schedule performance indices. This method is most useful when the project schedule is a factor impacting the ETC effort. Variations of this method weight the CPI and SPI at different values (e.g., 80/20, 50/50, or some other ratio) according to the project manager?s judgment. Equation: EAC = AC + [(BAC ? EV) / (CPI ž SPI)] Each of these approaches is applicable for any given project and will provide the project management team with an ?early warning? signal if the EAC forecasts are not within acceptable tolerances.

This definition was found in the PMBOK V5

Go back to the Glossary or to the Mapping

Leave a Reply

Your email address will not be published.